California State Dept of Transportation (CalTrans) is seeking bids from qualified and interested contractors for the following project titled, CONSTRUCTION ON STATE HIGHWAY IN PLACER COUNTY AT VARIOUS LOCATIONS FROM 0.3 MILE EAST OF CROTHER ROAD OVERCROSSING TO 0.3 MILE EAST OF PUTTS LAKE UNDERCROSSING In District 03 On Route 80 - Construct Truck Climbing Lanes & Replace Bridges., identified under Solicitation ID: 03-3H5904. Work is to be performed near Placer County, CA, USA in Placer County.
General Project Description
This project involves the construction of truck climbing lanes and the replacement of bridges on State Highway Route 80 in Placer County, California, across various locations. The work includes significant earthwork such as excavation and backfill for roadways and structures, concrete pavement installation and repair, hot mix asphalt paving, various drainage improvements including culverts and pipes, and extensive erosion control measures. Additionally, the project requires temporary traffic control systems, installation and removal of guardrails and barriers, a wide array of signage and pavement markings, and advanced electrical and communication infrastructure, including fiber optic cable systems, roadway weather information systems, camera systems, and changeable message signs. Management of treated wood waste and environmental product declarations for asphalt and concrete are also required.
General Bid Items
- Quantity: 1 Unit: LS Work Item: LEAD COMPLIANCE PLAN
- Quantity: 1 Unit: LS Work Item: LEVEL 2 CRITICAL PATH METHOD SCHEDULE
- Quantity: 1 Unit: LS Work Item: TIME-RELATED OVERHEAD (LS)
- Quantity: 19 Unit: EA Work Item: DISPUTE RESOLUTION BOARD ON-SITE MEETING
- Quantity: 380 Unit: HR Work Item: HOURLY OFF-SITE DISPUTE-RESOLUTION-BOARD-RELATED TASKS
- Quantity: 1 Unit: LS Work Item: SAFETY QUALITY CONTROL MANAGER
- Quantity: 1 Unit: LS Work Item: DEVELOP WATER SUPPLY
- Quantity: 1 Unit: LS Work Item: CONSTRUCTION AREA SIGNS
- Quantity: 1 Unit: LS Work Item: TRAFFIC CONTROL SYSTEM
- Quantity: 507000 Unit: LF Work Item: TEMPORARY TRAFFIC STRIPE (PAINT)
- Quantity: 94 Unit: EA Work Item: TRAFFIC DRUM
- Quantity: 1 Unit: EA Work Item: PORTABLE SIGNAL SYSTEMS (EA)
- Quantity: 142000 Unit: LF Work Item: TEMPORARY BARRIER SYSTEM
- Quantity: 1 Unit: LS Work Item: TEMPORARY PEDESTRIAN ACCESS ROUTE
- Quantity: 1 Unit: LS Work Item: PORTABLE CHANGEABLE MESSAGE SIGN (LS)
- Quantity: 86 Unit: EA Work Item: TEMPORARY CRASH CUSHION TL-3
- Quantity: 4 Unit: EA Work Item: TEMPORARY RADAR SPEED FEEDBACK SIGN SYSTEM
- Quantity: 300 Unit: DAY Work Item: AUTOMATED FLAGGER ASSISTANCE DEVICE
- Quantity: 1 Unit: LS Work Item: JOB SITE MANAGEMENT
- Quantity: 1 Unit: LS Work Item: STORMWATER POLLUTION PREVENTION PLAN
- Quantity: 256 Unit: EA Work Item: STORMWATER SAMPLING AND ANALYSIS DAY
- Quantity: 5 Unit: EA Work Item: STORMWATER ANNUAL REPORT
- Quantity: 1260 Unit: SQYD Work Item: TEMPORARY EROSION CONTROL BLANKET
- Quantity: 18 Unit: EA Work Item: MOVE-IN/MOVE-OUT (TEMPORARY EROSION CONTROL)
- Quantity: 438000 Unit: SQYD Work Item: TEMPORARY HYDRAULIC MULCH (BONDED FIBER MATRIX)
- Quantity: 10000 Unit: SQYD Work Item: TEMPORARY COVER
- Quantity: 27500 Unit: LF Work Item: TEMPORARY CHECK DAM
- Quantity: 160 Unit: EA Work Item: TEMPORARY DRAINAGE INLET PROTECTION
- Quantity: 25500 Unit: LF Work Item: TEMPORARY FIBER ROLL
- Quantity: 2440 Unit: LF Work Item: TEMPORARY GRAVEL BAG BERM
- Quantity: 12700 Unit: LF Work Item: TEMPORARY REINFORCED SILT FENCE
- Quantity: 1440 Unit: LF Work Item: TEMPORARY SILT FENCE
- Quantity: 33 Unit: EA Work Item: TEMPORARY CONSTRUCTION ENTRANCE
- Quantity: 1 Unit: LS Work Item: STREET SWEEPING
- Quantity: 1 Unit: LS Work Item: TEMPORARY CONCRETE WASHOUT
- Quantity: 20 Unit: EA Work Item: WATER QUALITY SAMPLING AND ANALYSIS DAY
- Quantity: 52 Unit: EA Work Item: WATER QUALITY MONITORING REPORT
- Quantity: 5 Unit: EA Work Item: WATER QUALITY ANNUAL REPORT
- Quantity: 1 Unit: LS Work Item: TEMPORARY CREEK DIVERSION SYSTEMS
- Quantity: 190000 Unit: LB Work Item: TREATED WOOD WASTE
- Quantity: 1 Unit: LS Work Item: CONTRACTOR-SUPPLIED BIOLOGIST (LS)
- Quantity: 25400 Unit: LF Work Item: REMOVE FIBER OPTIC CONDUIT
- Quantity: 4180 Unit: LF Work Item: TEMPORARY HIGH-VISIBILITY FENCE
- Quantity: 1 Unit: LS Work Item: CLEARING AND GRUBBING (LS)
- Quantity: 1 Unit: EA Work Item: REMOVE TREE
- Quantity: 286000 Unit: CY Work Item: ROADWAY EXCAVATION
- Quantity: 1414 Unit: CY Work Item: (F) - STRUCTURE EXCAVATION (BRIDGE)
- Quantity: 2895 Unit: CY Work Item: (F) - STRUCTURE EXCAVATION (SOLDIER PILE WALL)
- Quantity: 679 Unit: CY Work Item: (F) - STRUCTURE BACKFILL (BRIDGE)
- Quantity: 374 Unit: CY Work Item: (F) - STRUCTURE BACKFILL (SOLDIER PILE WALL)
- Quantity: 2702 Unit: CY Work Item: (F) - CONCRETE BACKFILL (SOLDIER PILE WALL)
- Quantity: 829 Unit: CY Work Item: (F) - LEAN CONCRETE BACKFILL
- Quantity: 2190 Unit: CY Work Item: DITCH EXCAVATION
- Quantity: 0.2 Unit: CY Work Item: SOIL AMENDMENT
- Quantity: 1.7 Unit: LB Work Item: ORGANIC FERTILIZER
- Quantity: 17 Unit: EA Work Item: PLANT (GROUP A)
- Quantity: 1 Unit: LS Work Item: PLANT ESTABLISHMENT WORK
- Quantity: 1 Unit: CY Work Item: WOOD MULCH
- Quantity: 1 Unit: LS Work Item: TEMPORARY IRRIGATION SYSTEM
- Quantity: 12 Unit: EA Work Item: MOVE-IN/MOVE-OUT (EROSION CONTROL)
- Quantity: 1990000 Unit: SQFT Work Item: HYDRAULIC BIOTIC GROWTH MEDIUM
- Quantity: 2000000 Unit: SQFT Work Item: FIBER REINFORCED MATRIX (SQFT)
- Quantity: 485000 Unit: SQFT Work Item: ROLLED EROSION CONTROL PRODUCT (NETTING)
- Quantity: 24600 Unit: LF Work Item: FIBER ROLLS
- Quantity: 190 Unit: CY Work Item: COMPOST
- Quantity: 70800 Unit: SQFT Work Item: INCORPORATE MATERIALS
- Quantity: 1 Unit: LS Work Item: PERMANENT EROSION CONTROL ESTABLISHMENT WORK
- Quantity: 1 Unit: LS Work Item: FINISHING ROADWAY
- Quantity: 37900 Unit: CY Work Item: CLASS 2 AGGREGATE BASE (CY)
- Quantity: 270 Unit: CY Work Item: RAPID STRENGTH CONCRETE BASE
- Quantity: 4590 Unit: SQYD Work Item: BASE BOND BREAKER
- Quantity: 84800 Unit: TON Work Item: HOT MIX ASPHALT (TYPE A)
- Quantity: 1300 Unit: SQYD Work Item: GEOSYNTHETIC PAVEMENT INTERLAYER (PAVING FABRIC)
- Quantity: 1120 Unit: LF Work Item: PLACE HOT MIX ASPHALT DIKE (TYPE A)
- Quantity: 1200 Unit: LF Work Item: PLACE HOT MIX ASPHALT DIKE (TYPE C)
- Quantity: 570 Unit: LF Work Item: PLACE HOT MIX ASPHALT DIKE (TYPE D)
- Quantity: 5800 Unit: LF Work Item: PLACE HOT MIX ASPHALT DIKE (TYPE E)
- Quantity: 2830 Unit: LF Work Item: PLACE HOT MIX ASPHALT DIKE (TYPE F)
- Quantity: 66 Unit: SQYD Work Item: PLACE HOT MIX ASPHALT (MISCELLANEOUS AREA)
- Quantity: 410 Unit: TON Work Item: TACK COAT
- Quantity: 406000 Unit: SQFT Work Item: REMOVE ASPHALT CONCRETE PAVEMENT
- Quantity: 2440 Unit: LF Work Item: REMOVE ASPHALT CONCRETE DIKE
- Quantity: 125000 Unit: SQYD Work Item: COLD PLANE ASPHALT CONCRETE PAVEMENT
- Quantity: 8340 Unit: CY Work Item: JOINTED PLAIN CONCRETE PAVEMENT
- Quantity: 2260 Unit: EA Work Item: DRILL AND BOND (DOWEL BAR)
- Quantity: 5610 Unit: EA Work Item: DRILL AND BOND (TIE BAR)
- Quantity: 350 Unit: CY Work Item: INDIVIDUAL SLAB REPLACEMENT (RSC)
- Quantity: 36800 Unit: LF Work Item: JOINT SEAL (ASPHALT RUBBER)
- Quantity: 9480 Unit: CY Work Item: REMOVE CONCRETE PAVEMENT AND BASE
- Quantity: 63400 Unit: SQYD Work Item: GRIND EXISTING CONCRETE PAVEMENT
- Quantity: 233 Unit: EA Work Item: GROUND ANCHOR (SUBHORIZONTAL)
- Quantity: 3860 Unit: SQFT Work Item: RAIL ELEMENT WALL
- Quantity: 90 Unit: LF Work Item: REMOVE RAIL ELEMENT WALL
- Quantity: 1 Unit: LS Work Item: TEMPORARY SUPPORT
- Quantity: 1575 Unit: LF Work Item: STEEL SOLDIER PILE (HP 14 X 117)
- Quantity: 697 Unit: LF Work Item: STEEL SOLDIER PILE (HP 16 X 141)
- Quantity: 9761 Unit: LF Work Item: STEEL SOLDIER PILE (2 - W 12 X 58)
- Quantity: 2291 Unit: LF Work Item: 30" DRILLED HOLE
- Quantity: 9319 Unit: LF Work Item: 42" DRILLED HOLE
- Quantity: 4500 Unit: LF Work Item: 24" CAST-IN-DRILLED-HOLE CONCRETE PILING
- Quantity: 111 Unit: LF Work Item: 78" CAST-IN-DRILLED-HOLE CONCRETE PILING
- Quantity: 429 Unit: LF Work Item: 16" CAST-IN-DRILLED-HOLE CONCRETE PILING (BARRIER)
- Quantity: 460 Unit: LF Work Item: 60" CAST-IN-DRILLED-HOLE CONCRETE PILE (SIGN FOUNDATION)
- Quantity: 114 Unit: CY Work Item: (F) - STRUCTURAL CONCRETE
- Quantity: 227 Unit: CY Work Item: (F) - STRUCTURAL CONCRETE, BRIDGE FOOTING
- Quantity: 645 Unit: CY Work Item: (F) - STRUCTURAL CONCRETE, BRIDGE
- Quantity: 590 Unit: CY Work Item: (F) - STRUCTURAL CONCRETE, BRIDGE (POLYMER FIBER)
- Quantity: 70 Unit: CY Work Item: STRUCTURAL CONCRETE, RETAINING WALL
- Quantity: 111 Unit: CY Work Item: (F) - STRUCTURAL CONCRETE, WINGWALL (TYPE A)
- Quantity: 1305 Unit: CY Work Item: (F) - STRUCTURAL CONCRETE, WALL FACING
- Quantity: 1004 Unit: CY Work Item: (F) - STRUCTURAL CONCRETE, BARRIER SLAB
- Quantity: 313 Unit: CY Work Item: (F) - STRUCTURAL CONCRETE, APPROACH SLAB (TYPE N)
- Quantity: 652 Unit: CY Work Item: (F) - STRUCTURAL CONCRETE, BOX CULVERT
- Quantity: 30 Unit: CY Work Item: (F) - STRUCTURAL CONCRETE, HEADWALL
- Quantity: 101 Unit: CY Work Item: (F) - STRUCTURAL CONCRETE, DRAINAGE INLET
- Quantity: 2143 Unit: SQFT Work Item: CONCRETE SURFACE TEXTURE (FRACTURED GRANITE)
- Quantity: 21333 Unit: SQFT Work Item: CONCRETE SURFACE TEXTURE (RANDOM ROUGH STACKED ROCK)
- Quantity: 10 Unit: EA Work Item: FURNISH PRECAST PRESTRESSED CONCRETE WIDE FLANGE GIRDER (120'-130')
- Quantity: 8 Unit: EA Work Item: FURNISH PRECAST PRESTRESSED CONCRETE WIDE FLANGE GIRDER (110'-120')
- Quantity: 18 Unit: EA Work Item: ERECT PRECAST PRESTRESSED CONCRETE GIRDER
- Quantity: 1849 Unit: LB Work Item: (F) - PIPE PIN
- Quantity: 135 Unit: LF Work Item: JOINT SEAL (MR 1")
- Quantity: 114 Unit: LF Work Item: JOINT SEAL (MR 1 1/2")
- Quantity: 237404 Unit: LB Work Item: (F) - BAR REINFORCING STEEL (BRIDGE)
- Quantity: 230271 Unit: LB Work Item: (F) - BAR REINFORCING STEEL (EPOXY COATED)
- Quantity: 362047 Unit: LB Work Item: (F) - BAR REINFORCING STEEL (WALL FACING, EPOXY COATED)
- Quantity: 64 Unit: EA Work Item: (F) - HEADED BAR REINFORCEMENT
- Quantity: 1160 Unit: LB Work Item: FURNISH SIGN STRUCTURE (BRIDGE MOUNTED WITHOUT WALKWAY)
- Quantity: 1160 Unit: LB Work Item: INSTALL SIGN STRUCTURE (BRIDGE MOUNTED WITHOUT WALKWAY)
- Quantity: 341000 Unit: LB Work Item: FURNISH SIGN STRUCTURE (VERSATILE TRUSS)
- Quantity: 341000 Unit: LB Work Item: INSTALL SIGN STRUCTURE (VERSATILE TRUSS)
- Quantity: 2410 Unit: SQFT Work Item: ALUMINUM WALKWAY GRATING (VERSATILE TRUSS)
- Quantity: 11 Unit: EA Work Item: REMOVE SIGN STRUCTURE (EA)
- Quantity: 1 Unit: EA Work Item: REMOVE BRIDGE MOUNTED SIGN
- Quantity: 182 Unit: MFBM Work Item: (F) - TIMBER LAGGING
- Quantity: 18318 Unit: SQFT Work Item: (F) - SOUND WALL (MASONRY BLOCK)
- Quantity: 1 Unit: LS Work Item: CLEAN AND PAINT STEEL SOLDIER PILING (LS)
- Quantity: 1 Unit: LS Work Item: PUBLIC SAFETY PLAN
- Quantity: 23168 Unit: SQFT Work Item: PREPARE CONCRETE BRIDGE DECK SURFACE
- Quantity: 3418 Unit: CF Work Item: FURNISH POLYESTER CONCRETE OVERLAY
- Quantity: 23168 Unit: SQFT Work Item: (F) - PLACE POLYESTER CONCRETE OVERLAY
- Quantity: 1 Unit: LS Work Item: BRIDGE REMOVAL, LOCATION A
- Quantity: 1 Unit: LS Work Item: BRIDGE REMOVAL, LOCATION B
- Quantity: 22 Unit: CY Work Item: (F) - CONCRETE BACKFILL (PIPE TRENCH)
- Quantity: 1370 Unit: LF Work Item: 24" REINFORCED CONCRETE PIPE
- Quantity: 590 Unit: LF Work Item: 18" CORRUGATED STEEL PIPE (.064" THICK)
- Quantity: 220 Unit: LF Work Item: 24" CORRUGATED STEEL PIPE (.064" THICK)
- Quantity: 100 Unit: LF Work Item: 30" CORRUGATED STEEL PIPE (.064" THICK)
- Quantity: 9 Unit: LF Work Item: 36" CORRUGATED STEEL PIPE (.064" THICK)
- Quantity: 36 Unit: LF Work Item: 42" CORRUGATED STEEL PIPE (.064" THICK)
- Quantity: 22 Unit: LF Work Item: 48" CORRUGATED STEEL PIPE (.064" THICK)
NAICS Classification
Highway, Street, and Bridge Construction (Core project work including truck climbing lanes, bridge replacement, and roadway improvements), Power and Communication Line and Related Structures Construction (Installation of fiber optic cable systems, electrical systems, traffic monitoring, camera, and roadway weather information systems), Other Heavy and Civil Engineering Construction (General heavy construction, including earth retaining systems, soldier piles, and various civil engineering tasks not specific to highways/bridges), Site Preparation Contractors (Clearing, grubbing, excavation, and earthwork related to site preparation), Poured Concrete Foundation and Structure Contractors (Concrete structures, retaining walls, bridge footings, barrier slabs, culverts, and concrete pavement components), Painting and Wall Covering Contractors (Coating and painting of structural steel, including soldier piles), Electrical Contractors and Other Wiring Installation Contractors (Temporary and permanent electrical work, traffic control systems, lighting, and communication infrastructure), Engineering Services (Contractor-supplied biologist, dispute resolution board tasks, safety and quality control management, water quality monitoring)
Records and Due Date
This bid opportunity was entered into BidAmerica on November 18, 2025, and was last updated on February 2, 2026. All bids and/or proposals are due on February 3, 2026.
Contractors may log in or create a free BidAmerica account to view full project documents, plans, specifications, addenda, submission requirements, and more project details issued by California State Dept of Transportation (CalTrans).
Legal Disclaimer
All bidders are responsible for reviewing and verifying all official bid documentation directly from the issuing agency. BidAmerica aggregates public bid information for advertisement purposes for contractors and government agencies convenience. This Notice of Invitation to Bid is for reference purposes only and is not an official or complete representation of any documents issued by California State Dept of Transportation (CalTrans). BidAmerica does not guarantee the accuracy, completeness, or timeliness of any information displayed and shall not be held liable for any errors, omissions, misinterpretations, or damages resulting from reliance on this summary. Contractors must obtain all official information—including plans, specifications, addenda, deadlines, submission requirements, qualifications, and bidding conditions—directly from California State Dept of Transportation (CalTrans) prior to bidding.