California State Dept of Transportation (CalTrans) is seeking bids from qualified and interested contractors for the following project titled, State Highway Construction & Pavement Maintenance on Route 280, San Francisco – Cold Plane, RHMA-G, Polyester Concrete Overlay, Replace PCC, & CMS System, identified under Solicitation ID: 04-0Q1204. Work is to be performed near 1120 N St, Sacramento, CA 95814, USA in Sacramento County.

General Project Description

This project involves construction on State Highway Route 280 in the City and County of San Francisco, stretching from the San Francisco County Line to Brannan Street, with specific work near 2800 Alemany Boulevard. The general scope includes cold planning, Rubberized Hot Mix Asphalt (RHMA-G) overlay, polyester concrete overlay, concrete barrier modifications, replacement of Portland Cement Concrete (PCC) pavement, and installation/replacement of Changeable Message Systems (CMS). Major works include extensive structural excavation and backfill for bridges, retaining walls, and soldier pile walls; drilling and installation of ground anchors, steel soldier piles, and cast-in-drilled-hole concrete piling; comprehensive landscaping and erosion control measures such as hydroseed, compost, fiber rolls, and irrigation systems; detailed temporary traffic control systems with barriers, signs, impact attenuators, and radar speed feedback; pavement markings and rumble strips (asphalt and concrete); electrical systems for traffic control devices and cellular routers; as well as ongoing vibration and crack monitoring, and careful management/disposal of regulated earth material containing lead and treated wood waste.

General Bid Items

  • Quantity: 1  Unit: LS  Work Item: LEAD COMPLIANCE PLAN
  • Quantity: 1  Unit: LS  Work Item: LEVEL 2 CRITICAL PATH METHOD SCHEDULE
  • Quantity: 500  Unit: WDAY  Work Item: TIME-RELATED OVERHEAD
  • Quantity: 11  Unit: EA  Work Item: DISPUTE RESOLUTION BOARD ON-SITE MEETING
  • Quantity: 60  Unit: HR  Work Item: HOURLY OFF-SITE DISPUTE-RESOLUTION-BOARD RELATED TASKS
  • Quantity: 1  Unit: LS  Work Item: SAFETY QUALITY CONTROL MANAGER
  • Quantity: 1  Unit: LS  Work Item: CONSTRUCTION AREA SIGNS
  • Quantity: 1  Unit: LS  Work Item: TRAFFIC CONTROL SYSTEM
  • Quantity: 30  Unit: DAY  Work Item: TRAFFIC CONTROL SUPERVISOR
  • Quantity: 500  Unit: DAY  Work Item: STATIONARY IMPACT ATTENUATOR VEHICLE
  • Quantity: 31700  Unit: LF  Work Item: TEMPORARY TRAFFIC STRIPE (PAINT)
  • Quantity: 600  Unit: EA  Work Item: CHANNELIZER (SURFACE MOUNTED)
  • Quantity: 720  Unit: DAY  Work Item: PORTABLE RADAR SPEED FEEDBACK SIGN SYSTEM
  • Quantity: 10900  Unit: LF  Work Item: TEMPORARY BARRIER SYSTEM
  • Quantity: 1  Unit: LS  Work Item: TEMPORARY SHUTTLE SERVICE
  • Quantity: 39  Unit: EA  Work Item: PORTABLE CHANGEABLE MESSAGE SIGN (EA)
  • Quantity: 40  Unit: DAY  Work Item: END OF QUEUE MONITORING AND WARNING WITH TRUCK MOUNTED CHANGEABLE MESSAGE SIGN
  • Quantity: 71  Unit: EA  Work Item: TEMPORARY CRASH CUSHION TL-3
  • Quantity: 2  Unit: EA  Work Item: TEMPORARY RADAR SPEED FEEDBACK SIGN SYSTEM
  • Quantity: 1  Unit: LS  Work Item: JOB SITE MANAGEMENT
  • Quantity: 1  Unit: LS  Work Item: STORMWATER POLLUTION PREVENTION PLAN
  • Quantity: 73  Unit: EA  Work Item: STORMWATER SAMPLING AND ANALYSIS DAY
  • Quantity: 3  Unit: EA  Work Item: STORMWATER ANNUAL REPORT
  • Quantity: 7200  Unit: SQYD  Work Item: TEMPORARY HYDRAULIC MULCH (BONDED FIBER MATRIX)
  • Quantity: 140  Unit: LF  Work Item: TEMPORARY CHECK DAM
  • Quantity: 160  Unit: EA  Work Item: TEMPORARY DRAINAGE INLET PROTECTION
  • Quantity: 4400  Unit: LF  Work Item: TEMPORARY FIBER ROLL
  • Quantity: 1  Unit: LS  Work Item: STREET SWEEPING
  • Quantity: 1  Unit: LS  Work Item: TEMPORARY CONCRETE WASHOUT
  • Quantity: 87000  Unit: LF  Work Item: REMOVE YELLOW THERMOPLASTIC TRAFFIC STRIPE (HAZARDOUS WASTE)
  • Quantity: 299000  Unit: LB  Work Item: TREATED WOOD WASTE
  • Quantity: 1  Unit: LS  Work Item: NOISE MONITORING
  • Quantity: 180  Unit: LF  Work Item: REMOVE CONCRETE (LF)
  • Quantity: 1  Unit: LS  Work Item: CLEARING AND GRUBBING (LS)
  • Quantity: 2420  Unit: CY  Work Item: ROADWAY EXCAVATION
  • Quantity: 2110  Unit: CY  Work Item: ROADWAY EXCAVATION (TYPE Z-2) (AERIALLY DEPOSITED LEAD)
  • Quantity: 233  Unit: CY  Work Item: (F) - STRUCTURE EXCAVATION (BRIDGE)
  • Quantity: 4500  Unit: CY  Work Item: (F) - STRUCTURE EXCAVATION (RETAINING WALL)
  • Quantity: 830  Unit: CY  Work Item: (F) - STRUCTURE EXCAVATION (SOLDIER PILE WALL)
  • Quantity: 91  Unit: CY  Work Item: (F) - STRUCTURE BACKFILL (BRIDGE)
  • Quantity: 4200  Unit: CY  Work Item: (F) - STRUCTURE BACKFILL (RETAINING WALL)
  • Quantity: 275  Unit: CY  Work Item: (F) - STRUCTURE BACKFILL (SOLDIER PILE WALL)
  • Quantity: 395  Unit: CY  Work Item: (F) - CONCRETE BACKFILL (SOLDIER PILE WALL)
  • Quantity: 225  Unit: CY  Work Item: (F) - LEAN CONCRETE BACKFILL
  • Quantity: 87  Unit: SQYD  Work Item: SUBGRADE ENHANCEMENT GEOTEXTILE, CLASS A1
  • Quantity: 1  Unit: LS  Work Item: ROADSIDE CLEARING
  • Quantity: 3940  Unit: SQFT  Work Item: ROCK BLANKET
  • Quantity: 6  Unit: CY  Work Item: SOIL AMENDMENT
  • Quantity: 250  Unit: EA  Work Item: PACKET FERTILIZER
  • Quantity: 210  Unit: EA  Work Item: PLANT (GROUP A)
  • Quantity: 12  Unit: EA  Work Item: PLANT (GROUP B)
  • Quantity: 3  Unit: EA  Work Item: PLANT (GROUP U)
  • Quantity: 1  Unit: LS  Work Item: PLANT ESTABLISHMENT WORK
  • Quantity: 6  Unit: CY  Work Item: WOOD MULCH
  • Quantity: 1  Unit: LS  Work Item: CHECK AND TEST EXISTING IRRIGATION FACILITIES
  • Quantity: 1  Unit: LS  Work Item: OPERATE EXISTING IRRIGATION FACILITIES
  • Quantity: 1  Unit: LS  Work Item: CONTROL AND NEUTRAL CONDUCTORS (ARMOR-CLAD)
  • Quantity: 5  Unit: EA  Work Item: 1 1/2" REMOTE CONTROL VALVE
  • Quantity: 1  Unit: EA  Work Item: 2" REMOTE CONTROL VALVE
  • Quantity: 1  Unit: EA  Work Item: 2" WYE STRAINER ASSEMBLY
  • Quantity: 1  Unit: EA  Work Item: 24-32 STATION IRRIGATION CONTROLLER (WALL MOUNTED)
  • Quantity: 10  Unit: LF  Work Item: (F) - 2 1/2" GALVANIZED STEEL PIPE (SUPPLY LINE)
  • Quantity: 1  Unit: LS  Work Item: CERTIFY EXISTING BACKFLOW PREVENTERS
  • Quantity: 1  Unit: EA  Work Item: 2" BACKFLOW PREVENTER ASSEMBLY
  • Quantity: 1  Unit: LS  Work Item: FLOW SENSOR CABLE
  • Quantity: 1  Unit: EA  Work Item: FLOW SENSOR
  • Quantity: 240  Unit: EA  Work Item: RISER SPRINKLER ASSEMBLY
  • Quantity: 4  Unit: EA  Work Item: 2 1/2" GATE VALVE
  • Quantity: 1890  Unit: LF  Work Item: (F) - 3/4" PLASTIC PIPE (SCHEDULE 40) (SUPPLY LINE)
  • Quantity: 33  Unit: LF  Work Item: (F) - 1" PLASTIC PIPE (SCHEDULE 40) (SUPPLY LINE)
  • Quantity: 1180  Unit: LF  Work Item: (F) - 1 1/2" PLASTIC PIPE (SCHEDULE 40) (SUPPLY LINE)
  • Quantity: 20  Unit: LF  Work Item: (F) - 2" PLASTIC PIPE (CLASS 315) (SUPPLY LINE)
  • Quantity: 830  Unit: LF  Work Item: (F) - 2 1/2" PLASTIC PIPE (CLASS 315) (SUPPLY LINE)
  • Quantity: 1  Unit: EA  Work Item: PRESSURE REGULATING VALVE
  • Quantity: 10  Unit: EA  Work Item: CHECK VALVE
  • Quantity: 1  Unit: EA  Work Item: 2" BALL VALVE
  • Quantity: 15  Unit: LF  Work Item: (F) - PVC PIPE CONDUIT (SLEEVE)
  • Quantity: 8  Unit: EA  Work Item: MOVE-IN/MOVE-OUT (EROSION CONTROL)
  • Quantity: 34300  Unit: SQFT  Work Item: ROLLED EROSION CONTROL PRODUCT (NETTING)
  • Quantity: 53200  Unit: SQFT  Work Item: HYDROMULCH
  • Quantity: 27700  Unit: LF  Work Item: FIBER ROLLS
  • Quantity: 172000  Unit: SQFT  Work Item: HYDROSEED
  • Quantity: 250  Unit: CY  Work Item: COMPOST
  • Quantity: 18900  Unit: SQFT  Work Item: INCORPORATE MATERIALS
  • Quantity: 1  Unit: LS  Work Item: PERMANENT EROSION CONTROL ESTABLISHMENT WORK
  • Quantity: 19  Unit: CY  Work Item: CLASS 2 AGGREGATE BASE (CY)
  • Quantity: 78  Unit: TON  Work Item: PRIME COAT
  • Quantity: 160  Unit: TON  Work Item: HOT MIX ASPHALT (TYPE A)
  • Quantity: 22900  Unit: TON  Work Item: RUBBERIZED HOT MIX ASPHALT (GAP GRADED)
  • Quantity: 1940  Unit: LF  Work Item: PLACE HOT MIX ASPHALT DIKE (TYPE C)
  • Quantity: 9380  Unit: LF  Work Item: PLACE HOT MIX ASPHALT DIKE (TYPE F)
  • Quantity: 23  Unit: TON  Work Item: TACK COAT
  • Quantity: 11500  Unit: LF  Work Item: REMOVE ASPHALT CONCRETE DIKE
  • Quantity: 174000  Unit: SQYD  Work Item: COLD PLANE ASPHALT CONCRETE PAVEMENT
  • Quantity: 7  Unit: CY  Work Item: REMOVE BASE AND SURFACING
  • Quantity: 1330  Unit: CY  Work Item: INDIVIDUAL SLAB REPLACEMENT (RSC)
  • Quantity: 28700  Unit: SQYD  Work Item: GRIND EXISTING CONCRETE PAVEMENT
  • Quantity: 67  Unit: EA  Work Item: GROUND ANCHOR (SUBHORIZONTAL)
  • Quantity: 2365  Unit: LF  Work Item: STEEL SOLDIER PILE (2-W 16 X 50)
  • Quantity: 2375  Unit: LF  Work Item: 36" DRILLED HOLE
  • Quantity: 5556  Unit: LF  Work Item: 24" CAST-IN-DRILLED-HOLE CONCRETE PILING
  • Quantity: 160  Unit: LF  Work Item: 60" CAST-IN-DRILLED-HOLE CONCRETE PILING
  • Quantity: 76  Unit: LF  Work Item: 60" CAST-IN-DRILLED-HOLE CONCRETE PILE (SIGN FOUNDATION)
  • Quantity: 27  Unit: CY  Work Item: (F) -

NAICS Classification

237310 – Highway, Street, and Bridge Construction (General highway construction, paving, bridge work, concrete structures, and related infrastructure improvements), 238910 – Site Preparation Contractors (For clearing, grubbing, various types of excavation, and erosion control establishment), 237990 – Other Heavy and Civil Engineering Construction (Specialized heavy construction components like soldier pile walls, ground anchors, and concrete piling), 238110 – Poured Concrete Foundation and Structure Contractors (Placement of structural concrete for bridge footings, retaining walls, pile caps, and barrier slabs), 238120 – Structural Steel and Precast Concrete Contractors (Installation of steel soldier piles, reinforcing steel, guardrail systems, and precast concrete barriers), 238210 – Electrical Contractors and Other Wiring Installation Contractors (Installation and maintenance of electrical systems, changeable message signs, and cellular routers for traffic control devices), 238320 – Painting and Wall Covering Contractors (Cleaning and painting of structural steel, and application of pavement markings), 561730 – Landscaping Services (Plant establishment, irrigation system installation and operation, erosion control materials, and weed/pest control), 541330 – Engineering Services (For specialized monitoring, survey, and plan development including vibration, crack, and environmental aspects required from qualified professionals)

Records and Due Date

This bid opportunity was entered into BidAmerica on December 8, 2025, and was last updated on February 9, 2026. All bids and/or proposals are due on February 12, 2026.

Contractors may log in or create a free BidAmerica account to view full project documents, plans, specifications, addenda, submission requirements, and more project details issued by California State Dept of Transportation (CalTrans).

Legal Disclaimer

All bidders are responsible for reviewing and verifying all official bid documentation directly from the issuing agency. BidAmerica aggregates public bid information for advertisement purposes for contractors and government agencies convenience. This Notice of Invitation to Bid is for reference purposes only and is not an official or complete representation of any documents issued by California State Dept of Transportation (CalTrans). BidAmerica does not guarantee the accuracy, completeness, or timeliness of any information displayed and shall not be held liable for any errors, omissions, misinterpretations, or damages resulting from reliance on this summary. Contractors must obtain all official information—including plans, specifications, addenda, deadlines, submission requirements, qualifications, and bidding conditions—directly from California State Dept of Transportation (CalTrans) prior to bidding.

State Highway Construction & Pavement Maintenance on Route 280, San Francisco – Cold Plane, RHMA-G, Polyester Concrete Overlay, Replace PCC, & CMS System - Bid Opportunity | BidAmerica