Loading...
Unofficial Notice of Invitation to Bid (NIB)
Garden Grove City is seeking bids from qualified and interested contractors for the following project titled, SEWER SYSTEM REHABILITATION PLAN PHASE I I SEWER MAIN LINING AND SPOT REPAIR PROJECT 1, identified under Solicitation ID: CP1364000. Work is to be performed near 11222 Acacia Pkwy, Garden Grove, CA 92840, USA in Orange County.
General Project Description
This project, "SEWER SYSTEM REHABILITATION PLAN PHASE I I SEWER MAIN LINING AND SPOT REPAIR PROJECT 1," involves the rehabilitation of approximately 19,980 linear feet of existing 8-inch, 10-inch, 12-inch, and 15-inch vitrified clay pipe (VCP) sewer mains within a residential neighborhood bounded by Euclid Street, Harbor Boulevard, Katella Avenue, and Chapman Avenue in Garden Grove. The work includes UV-cured, glass fiber-reinforced Cured-in-Place Pipe (GRP-CIPP) lining for the majority of pipe segments, targeted open-cut spot repairs totaling approximately 4 segments of 6 LF each, robotic reinstatement of 430 active laterals, and installation of 83 Top Hat liners to ensure watertight connections. Supporting activities include mobilization/demobilization (including permitting), traffic control, stormwater pollution control, preliminary and final CCTV inspection, heavy cleaning, and temporary bypass facilities.
General Bid Items
- Quantity: 1 Unit: LS Work Item: Mobilization/Demobilization (Includes permitting, all cleanup, and punchlist items)
- Quantity: 1 Unit: LS Work Item: Prepare Traffic Control Plans, Project Information Sign, and Implement in the Field
- Quantity: 1 Unit: LS Work Item: Stormwater and Non-Stormwater Pollution Control
- Quantity: 19910 Unit: LF Work Item: Perform Preliminary and Final CCTV Inspection, Heavy Cleaning, Including Cutting, Removal and Disposal of Deposits, Roots, Intruding Laterals, Debris and Obstructions Where Required (Includes all labor, materials, tools, equipment, incidentals, transportation and handling)
- Quantity: 16541 Unit: LF Work Item: Furnish and Install 8 -Inch Diameter UV -Cured, Glass Fiber -Reinforced Cured- In-Place Pipe (GRP -CIPP) Liner (Includes all labor, materials, tools, equipment, incidentals, transportation, handling, sampling and lab testing)
- Quantity: 918 Unit: LF Work Item: Furnish and Install 10 -inch Diameter UV -Cured, Glass Fiber -Reinforced Cured- In-Place Pipe (GRP -CIPP) Liner (Includes all labor, materials, tools, equipment, incidentals, transportation, handling, sampling and lab testing)
- Quantity: 1633 Unit: LF Work Item: Furnish and Install 12-inch Diameter UV -Cured, Glass Fiber -Reinforced Cured- In-Place Pipe (GRP -CIPP) Liner (Includes all labor, materials, tools, equipment, incidentals, transportation, handling, sampling and lab testing)
- Quantity: 819 Unit: LF Work Item: Furnish and Install 15- inch Diameter UV -Cured, Glass Fiber -Reinforced Cured- In-Place Pipe (GRP -CIPP) Liner (Includes all labor, materials, tools, equipment, incidentals, transportation, handling, sampling and lab testing)
- Quantity: 1 Unit: LS Work Item: Perform Point Repair on Pipe 6228 from STA 10+76± to STA 10+82 ±, Trench Shoring, Backfill and Compaction, Pavement Restoration, and Striping (Includes all labor, materials, tools, equipment, incidentals, transportation and handling)
- Quantity: 1 Unit: LS Work Item: Perform Point Repair on Pipe 6185 from STA 12+92 ± to STA 12+98±, Trench Shoring, Backfill and Compaction, Pavement Restoration, and Striping (Includes all labor, materials, tools, equipment, incidentals, transportation and handling)
- Quantity: 1 Unit: LS Work Item: Perform Point Repair on Pipe 5969 from STA 10+00 ± to STA 10+06+, Trench Shoring, Backfill and Compaction, Pavement Restoration, and Striping (Includes all labor, materials, tools, equipment, incidentals, transportation and handling)
- Quantity: 430 Unit: EA Work Item: Grind and Reinstate Service Lateral Openings (Includes all labor, materials, tools, equipment, incidentals, transportation and handling)
- Quantity: 83 Unit: EA Work Item: Install 4 -Inch and 6 -Inch Diameter Top Hat Liner (Includes all labor, materials, tools, equipment, incidentals, transportation and handling)
- Quantity: 1 Unit: LS Work Item: Temporary Bypass Facilities (Includes all labor, materials, tools, equipment, incidentals, transportation and handling)
NAICS Classification
NAICS 237110 – Water and Sewer Line and Related Structures Construction, NAICS 238910 – Site Preparation Contractors, NAICS 238290 – Other Building Equipment Contractors
Records and Due Date
This bid opportunity was entered into BidAmerica on February 27, 2026, and was last updated on February 27, 2026. All bids and/or proposals are due on March 23, 2026.
Contractors may log in or create a free BidAmerica account to view full project documents, plans, specifications, addenda, submission requirements, and more project details issued by Garden Grove City.
Legal Disclaimer
All bidders are responsible for reviewing and verifying all official bid documentation directly from the issuing agency. BidAmerica aggregates public bid information for advertisement purposes for contractors and government agencies convenience. This Notice of Invitation to Bid is for reference purposes only and is not an official or complete representation of any documents issued by Garden Grove City. BidAmerica does not guarantee the accuracy, completeness, or timeliness of any information displayed and shall not be held liable for any errors, omissions, misinterpretations, or damages resulting from reliance on this summary. Contractors must obtain all official information—including plans, specifications, addenda, deadlines, submission requirements, qualifications, and bidding conditions—directly from Garden Grove City prior to bidding.