Long Beach Unified School District is seeking bids from qualified and interested contractors for the following project titled, MDF/IDF SWITCH REPLACEMENT PROJECT (E-RATE FUNDING YEAR 2026), identified under Solicitation ID: 2526-007-RFP. Work is to be performed near 4400 Ladoga Ave room 29, Lakewood, CA 90713, USA in Los Angeles County.
General Project Description
The Long Beach Unified School District (LBUSD) is seeking a qualified vendor to replace aging Cisco core Main Distribution Frame (MDF) and Intermediate Distribution Frame (IDF) access switches at multiple school locations within the LBUSD boundaries. The project’s scope includes comprehensive tasks such as planning, collaboration, and implementation of new Cisco 9500 (MDF) and 9300 (IDF) switches. Work also involves system testing and verification, post-installation support, and remediation. This entails the physical removal and disposal of older switches (Cisco ASR, chassis-based core switches, Catalyst switches, UPS systems, XPS systems), integration of new switches with the existing LBUSD Cisco DNA appliance, and standardization of deployment methodologies, including thorough cable management (new MONOPRICE SLIMRUN CAT6A Ethernet Cables), cleanup of rack installations, and replacement of fiber patch cables and SFPs. All disruptive work must occur after school hours, and the contractor must provide a 90-day workmanship warranty.
General Bid Items
- Quantity: 1 Unit: LS Work Item: Coordination with LBUSD Information Technology for IP addresses and naming conventions
- Quantity: 1 Unit: LS Work Item: Provide a detailed project plan (Excel format preferred) within two weeks of Notice To Proceed
- Quantity: Multiple Unit: EA Work Item: Replace existing switches at MDF with Cisco 9500 switches
- Quantity: Multiple Unit: EA Work Item: Replace existing switches at IDF with Cisco 9300 switches
- Quantity: Multiple Unit: EA Work Item: Removal and disposal of old Cisco ASR and chassis-based core switches (4500 or 6000 series)
- Quantity: Multiple Unit: EA Work Item: Removal and disposal of old Cisco Catalyst switches (3560x typically)
- Quantity: Multiple Unit: EA Work Item: Removal and disposal of old UPS systems/batteries
- Quantity: Multiple Unit: EA Work Item: Removal and disposal of old XPS systems
- Quantity: 1 Unit: LS Work Item: Integrate new switches into existing LBUSD Cisco DNA appliance
- Quantity: Multiple Unit: EA Work Item: Physical installation of new switches with migration of existing network functionality
- Quantity: 1 Unit: LS Work Item: Configure new switches to be managed via Cisco DNA (inventory management, software updating, troubleshooting)
- Quantity: Multiple Unit: EA/LS Work Item: Transfer standalone ASR router functions to integrated function on Cisco 9500 core switch
- Quantity: Multiple Unit: EA/LS Work Item: Transfer physical fiber/copper cable connections to 9500 Core Switch
- Quantity: Multiple Unit: EA Work Item: Decommission and remove physical ASR router
- Quantity: Multiple Unit: EA Work Item: Label new switches; Specifications: plastic labels, 3.94x2.28 inch (100x58 mm) writing area, 10 inch (225mm) overall wirelength, including Switch Name, IP, SN, Stack ID, and QR code
- Quantity: Multiple Unit: EA Work Item: Label IDF cabinets with new assigned IDF numbering scheme
- Quantity: Various Unit: LF Work Item: Replace existing Fiber Patch Cables at MDF (ST or SC Type)
- Quantity: Various Unit: LF Work Item: Replace damaged or inappropriate length fiber cables at IDF
- Quantity: Multiple Unit: EA Work Item: Replace damaged SFPs at IDF
- Quantity: Multiple Unit: EA Work Item: Replace older GBICs at core MDF switch with new SFPs
- Quantity: 1 Unit: LS Work Item: Cleanup and organization of rack space
- Quantity: Various Unit: LF Work Item: Replace all existing patch cables with new blue MONOPRICE SLIMRUN CAT6A 30AWG Ethernet Cables; Specifications: appropriate patch cable lengths (3-foot for 1U-5U spacing, 5-foot for 5U-8U spacing, 7-foot for 8U and beyond), 5-foot length for bidding purposes
- Quantity: 1 Unit: LS Work Item: Assemble basic cable management (Velcro or other reusable strapping)
- Quantity: Various Unit: LF Work Item: Install split loom tubing to protect Fiber Optical patch cables (secured to prevent snagging)
- Quantity: 1 Unit: LS Work Item: Cable manage power supply cables
- Quantity: 1 Unit: LS Work Item: Adjust rails in rack to accommodate new equipment
- Quantity: Multiple Unit: EA Work Item: Removal and decommissioning of identified UPS systems (XPS2200 rack mounted power units)
- Quantity: Multiple Unit: EA Work Item: Replace removed UPS with Tripp Lite Isobar PDU at IDF cabinet; Specifications: placed on 2nd to last U of IDF cabinet
- Quantity: Daily Unit: LS Work Item: Perform nightly clean-up
- Quantity: Per Site Unit: N/A Work Item: Provide photographic evidence of complete installation for each MDF/IDF (Front view, front view with door open, bottom view of PDU, cabinet open from back)
- Quantity: Per Site Unit: N/A Work Item: Provide Final Installation Report Checklist
- Quantity: 1 Unit: LS Work Item: Provide up to 4 hours of training (2 separate events)
- Quantity: 1 Unit: LS Work Item: Provide post-installation day 1 support (7am-11am onsite skilled resource)
- Quantity: 1 Unit: LS Work Item: Provide 90-day workmanship warranty
- Quantity: 1 Unit: LS Work Item: Decommission old existing equipment (switches, UPS, XPS power switches, cables)
- Quantity: 1 Unit: LS Work Item: Dispose of all trash and recycling generated by the project
- Quantity: 1 Unit: LS Work Item: Document asset tags of existing equipment removed
- Quantity: 1 Unit: LS Work Item: Deliver and unload old equipment to LBUSD warehouse/IT offices
NAICS Classification
NAICS 238210 – Electrical Contractors and Other Wiring Installation Contractors (Installation of network cabling, patch panels, fiber cables, and associated electrical components for switches)., NAICS 541512 – Computer Systems Design Services (Planning, configuration, system testing, integration of new Cisco network switches and DNA appliance, network topology mapping, and documentation)., NAICS 811212 – Computer and Office Machine Repair and Maintenance (Post-installation support, remediation, and providing a 90-day workmanship warranty for newly installed network equipment).
Records and Due Date
This bid opportunity was entered into BidAmerica on December 8, 2025, and was last updated on December 5, 2025. All bids and/or proposals are due on January 7, 2026.
Contractors may log in or create a free BidAmerica account to view full project documents, plans, specifications, addenda, submission requirements, and more project details issued by Long Beach Unified School District.
Legal Disclaimer
All bidders are responsible for reviewing and verifying all official bid documentation directly from the issuing agency. BidAmerica aggregates public bid information for advertisement purposes for contractors and government agencies convenience. This Notice of Invitation to Bid is for reference purposes only and is not an official or complete representation of any documents issued by Long Beach Unified School District. BidAmerica does not guarantee the accuracy, completeness, or timeliness of any information displayed and shall not be held liable for any errors, omissions, misinterpretations, or damages resulting from reliance on this summary. Contractors must obtain all official information—including plans, specifications, addenda, deadlines, submission requirements, qualifications, and bidding conditions—directly from Long Beach Unified School District prior to bidding.