Santa Paula City is seeking bids from qualified and interested contractors for the following project titled, PARK STREET/ORCHARD STREET WATER, SEWER, PAVING PROJECT, identified under Solicitation ID: 19-01896. Work is to be performed near 866 E Main St, Santa Paula, CA 93060, USA in Ventura County.

General Project Description

This public works project involves improvements on Park and Orchard Streets in the City of Santa Paula. The scope includes the installation of approximately 1,500 linear feet of 8-inch diameter potable water pipeline, including removal of existing pipes, connections to water mains, temporary water highline system, pavement removal, excavation, thrust blocks, miscellaneous water improvements, pressure testing, flushing, disinfection, bacteriological testing, backfill, compaction, and replacement trench paving. Additionally, it requires the removal of 325 linear feet of existing 6-inch diameter VCP sewer pipe and replacement with 6-inch diameter PVC pipe, manhole replacement, pavement grind and 2.5-inch overlay for both streets, digout areas, minor curb and gutter replacement, and sidewalk replacement, along with other incidental and appurtenant work.

General Bid Items

  • Quantity: 1,500  Unit: LF  Work Item: Installation of 8-inch diameter potable water pipeline
  • Quantity: -  Unit: -  Work Item: Removal of existing water pipeline in areas of conflicts.
  • Quantity: -  Unit: -  Work Item: Related connections to existing water mains and improvements.
  • Quantity: -  Unit: -  Work Item: Temporary water highline system.
  • Quantity: -  Unit: -  Work Item: Pavement removal.
  • Quantity: -  Unit: -  Work Item: Excavation.
  • Quantity: -  Unit: -  Work Item: Thrust blocks.
  • Quantity: -  Unit: -  Work Item: Miscellaneous water improvements.
  • Quantity: -  Unit: -  Work Item: Pressure testing of water line.
  • Quantity: -  Unit: -  Work Item: Flushing and disinfection of water line.
  • Quantity: -  Unit: -  Work Item: Bacteriological testing of water line.
  • Quantity: -  Unit: -  Work Item: Backfill and compaction.
  • Quantity: -  Unit: -  Work Item: Replacement trench paving.
  • Quantity: 325  Unit: LF  Work Item: Removal of existing 6-inch diameter VCP sewer pipe.
  • Quantity: -  Unit: -  Work Item: Replacement with 6-inch diameter PVC sewer pipe.
  • Quantity: -  Unit: -  Work Item: Manhole replacement.
  • Quantity: -  Unit: -  Work Item: Pavement grind for both streets.
  • Quantity: -  Unit: -  Work Item: 2.5 inch overlay for both streets.
  • Quantity: -  Unit: -  Work Item: Digout areas.
  • Quantity: -  Unit: -  Work Item: Minor curb and gutter replacement.
  • Quantity: -  Unit: -  Work Item: Sidewalk replacement.
  • Quantity: -  Unit: -  Work Item: Incidental and appurtenant work.

NAICS Classification

NAICS 237110 – Water and Sewer Line and Related Structure Construction, NAICS 237310 – Highway, Street, and Bridge Construction, NAICS 238910 – Site Preparation Contractors, NAICS 238190 – Other Foundation, Structure, and Building Exterior Contractors

Records and Due Date

This bid opportunity was entered into BidAmerica on February 10, 2026, and was last updated on February 11, 2026. All bids and/or proposals are due on March 12, 2026.

Contractors may log in or create a free BidAmerica account to view full project documents, plans, specifications, addenda, submission requirements, and more project details issued by Santa Paula City.

Legal Disclaimer

All bidders are responsible for reviewing and verifying all official bid documentation directly from the issuing agency. BidAmerica aggregates public bid information for advertisement purposes for contractors and government agencies convenience. This Notice of Invitation to Bid is for reference purposes only and is not an official or complete representation of any documents issued by Santa Paula City. BidAmerica does not guarantee the accuracy, completeness, or timeliness of any information displayed and shall not be held liable for any errors, omissions, misinterpretations, or damages resulting from reliance on this summary. Contractors must obtain all official information—including plans, specifications, addenda, deadlines, submission requirements, qualifications, and bidding conditions—directly from Santa Paula City prior to bidding.

PARK STREET/ORCHARD STREET WATER, SEWER, PAVING PROJECT - Bid Opportunity | BidAmerica