General Project Description
The City of Santa Ana is soliciting proposals for professional engineering services related to the Santiago Creek Pedestrian Bridge Improvements. This project entails the demolition of the existing 112-foot long, 3-span pedestrian bridge (connecting North Baker Street and West River Lane) and the design and construction support for a new pedestrian bridge. The comprehensive scope includes preparing environmental documents, detailed plans, specifications, and cost estimates for bridge replacement, structural and civil engineering design adhering to AASHTO and Caltrans standards, ADA curb ramp design, right-of-way engineering, electrical design for bridge lighting, and various environmental impact studies and regulatory permitting. The selected consultant will also provide public outreach and construction support services.
General Bid Items
- Quantity: - Unit: - Work Item: Project Coordination and Management. Specs: Organize and participate in project development team meetings, prepare progress reports, coordinate with public agencies and utility companies, obtain necessary permits for field investigations.
- Quantity: - Unit: - Work Item: Records Research. Specs: Collect and review all existing data relevant to the project, including existing site conditions, as-built and record drawings, right-of-way information, and planned improvements.
- Quantity: - Unit: - Work Item: Topographic Survey. Specs: Conduct a comprehensive topographic field survey to identify and map all existing features (channel topography, curb & gutter, sidewalk, right-of-way, parkway facilities, decorative lighting/streetlight poles, underground utilities, utility manholes/pull boxes, fencing, ADA ramps, bridge deck/columns, electrical points of connection, street tie-ins, grade breaks, survey monuments, vertical control at 0.5-foot contour intervals, joint elevations at right-of-way lines).
- Quantity: - Unit: - Work Item: Conceptual Bridge Designs. Specs: Prepare three conceptual designs, including ADA-compliant access points through switchback ramp systems and stair access for non-ADA users.
- Quantity: - Unit: - Work Item: Bridge 3D Modeling and Visuals.
- Quantity: - Unit: - Work Item: NPDES Water Quality Management Plan (WQMP) preparation. Specs: Determine if project triggers WQMP per North Orange County NPDES Permit requirements; if so, prepare WQMP in accordance with TGD; investigate soil contamination, erosion, groundwater, soil composition, infiltration rate, structural stability, hydromodification, utility conflicts, and perform soil/infiltration testing.
- Quantity: - Unit: - Work Item: Environmental & Regulatory Compliance. Specs: Prepare, process, and complete environmental documentation per California Environmental Quality Act (CEQA) and National Environmental Policy Act (NEPA); prepare permits including U.S. Army Corps of Engineers Sections 404 and 408 Permits, California Department of Fish and Wildlife (CDFW) Section 1601 Agreement, National Pollutant Discharge Elimination System (NPDES) Permits, Regional Water Quality Control Board Section 401 Certification, Orange County Public Works Encroachment Permit; assess potential hazardous materials and recommend mitigation.
- Quantity: - Unit: - Work Item: Hydrology/Hydraulic Analyses and Modeling. Specs: Prepare all necessary technical studies and reports.
- Quantity: - Unit: - Work Item: Geotechnical Studies/Reports/Boring/Infiltration Testing. Specs: Prepare geotechnical studies and reports.
- Quantity: - Unit: - Work Item: Bridge Lighting Design. Specs: Prepare bridge lighting design plans, specifications, and cost for bridge deck, ADA access ramps, and approach areas, incorporating energy efficiency (LED fixtures, controls), glare minimization, and adequate illumination for pedestrian safety.
- Quantity: - Unit: - Work Item: Electrical Engineering Design. Specs: Prepare electrical design plans and specifications for pedestrian bridge improvements and associated project elements, including power distribution, lighting systems, irrigation system, electrical service coordination, conduit and wiring layouts, and required electrical appurtenances.
- Quantity: - Unit: - Work Item: Traffic Signage Design. Specs: Design permanent and, if required, temporary signage addressing pedestrian safety, ADA accessibility, and interface with adjacent roadways, walkways, or public right-of-way, complying with MUTCD and applicable City/County standards. Identify sign types, locations, mounting details, materials, and prepare specifications for bidding and construction.
- Quantity: - Unit: - Work Item: Public Outreach. Specs: Prepare materials and allow for three public outreach meetings, access coordination, and one council meeting presentation.
- Quantity: - Unit: - Work Item: Plans, Specifications, and Estimates (PS&E) Development. Specs: Develop detailed PS&E, including adherence to City and Caltrans design standards, plan certification, calculations, and deliverables; prepare quantity calculations and cost estimates; submit electronic CADD files, reports, and calculations. Includes 30%, 60%, 90% (pre-final) and 100% (final) milestone deliverables.
- Quantity: - Unit: - Work Item: Construction Documents (CDs). Specs: Finalize approved deliverables from Design Development phase, including detailed engineering and construction drawings, structural calculations, final technical specifications, finalized “Opinion of Probable Cost”, and constructability review. Plans include Title Sheet, Architectural Design, Civil Engineering (Construction Staging Plan, Site Erosion Plan, Horizontal and Vertical Control Plan, Site Utility Plan, ADA Ramps or access), Structural Engineering (Design and Detailing), Bridge Lighting (Layout Plan and Details), Landscaping & Irrigation, Traffic Engineering (Signage and Details), and Pedestrian and bicycle accommodations & detour plan.
- Quantity: - Unit: - Work Item: Value Engineering and Cost Control. Specs: Actively pursue value engineering and cost-control opportunities, evaluate alternative materials, systems, and construction methods, and perform ongoing cost monitoring.
- Quantity: - Unit: - Work Item: Bid Advertisement and Support. Specs: Provide support to the City during the Bidding phase, assisting with questions, requests for information/clarification, or conflicts, and attend pre-bid meeting if scheduled.
- Quantity: - Unit: - Work Item: Construction Administration. Specs: Provide support to the City during the Construction Administration phase, assist with questions/RFIs, review submittals/shop drawings, complete shop drawing reviews within two (2) weeks, complete Contract Change Order reviews within two (2) working days, resolve discrepancies, and bring defects to the City's attention.
- Quantity: - Unit: - Work Item: Quality Assurance and Quality Control (QA/QC) Plan. Specs: Implement a QA/QC plan to ensure accuracy and completeness of plans, designs, specifications, and estimates, including independent checking and back checking.
NAICS Classification
541330 – Engineering Services (Bridge design, structural analysis, civil engineering, electrical design, hydraulic analysis, geotechnical studies), 541370 – Surveying and Mapping Services (Topographic survey, right-of-way engineering), 541620 – Environmental Consulting Services (Environmental impact studies, permitting assistance, hazardous materials assessment), 541310 – Architectural Services (Architectural design, bridge 3D modeling and visuals, landscaping design)
Records and Due Date
This bid opportunity was entered into BidAmerica on February 11, 2026, and was last updated on February 11, 2026. All bids and/or proposals are due on February 24, 2026.
Contractors may log in or create a free BidAmerica account to view full project documents, plans, specifications, addenda, submission requirements, and more project details issued by Santa Ana City.
Legal Disclaimer
All bidders are responsible for reviewing and verifying all official bid documentation directly from the issuing agency. BidAmerica aggregates public bid information for advertisement purposes for contractors and government agencies convenience. This Notice of Invitation to Bid is for reference purposes only and is not an official or complete representation of any documents issued by Santa Ana City. BidAmerica does not guarantee the accuracy, completeness, or timeliness of any information displayed and shall not be held liable for any errors, omissions, misinterpretations, or damages resulting from reliance on this summary. Contractors must obtain all official information—including plans, specifications, addenda, deadlines, submission requirements, qualifications, and bidding conditions—directly from Santa Ana City prior to bidding.